Pasir Gudang Hospital, which is under construction, is expected to be fully operational in April next year, ahead of schedule, said Deputy Works Minister Ahmad Maslan.
He said the hospital’s construction is 83.55 percent complete, compared to 72.50 percent under the original schedule.
“This project...