Most Read
Most Commented
mk-logo
News
ECRL's Kota Bharu-Dungun proposed realignment to be unveiled on Monday

The East Coast Rail Link project will unveil its proposed realignment from Kota Bharu to Dungun during its public inspection exercise on Nov 25, according to Malaysia Rail Link Sdn Bhd (MRL) in a statement today.

It said the public can give feedback and suggestions during the three-month ECRL public inspection for the Kota Bharu-Dungun stretch (also known as Section A), comprising a 210.4km mainline, a proposed 14.4 km future spur line, and six-passenger/ freight stations.

The ECRL realignment for Section A had proposed two stations for Kelantan namely Kota Bharu and Pasir Puteh, while Terengganu will have four stations located at Jerteh, Bandar Permaisuri, Kuala Terengganu, and Dungun.

The 14.4km proposed future spur line is expected to link the ECRL mainline in Kelantan with the port of Tok Bali.

The proposed 210.4km Kota Bharu-Dungun stretch or Section A mainline will consist of 43.9km rail alignment in Kelantan and the remaining 166.5km alignment in Terengganu.

MRL CEO Darwis Abdul Razak said the proposed realignment for Section A was in line with the comprehensive value engineering exercise that resulted in cost savings for the improved ECRL project.

The 210.4km stretch, he said, would be positioned inland instead of the coastal areas of Kelantan and Terengganu.

Darwis said MRL had received conditional approval for its ECRL Railway Scheme for Section A from Agensi Pengangkutan Awam Darat (Apad) on Nov 4, paving the way for the public inspection exercise to ensure the project’s rail alignment meet the interests and expectations of the local populace.

The public inspection information booth for Section A will operate on weekdays at Apad headquarters in Kuala Lumpur from Nov 25, 2019, until Feb 24, 2020.

“We have also initiated the environment impact assessment, social impact assessment, and heritage impact assessment for Section A to the authorities as these reports are prerequisites for Apad granting final approval to our Railway Scheme.

“The public may also visit MRL’s website or access the ECRL project’s social media platform for the latest information and details of the public inspection exercise,” he said.

On ECRL’s progress, Darwis said the project’s overall completion rate currently stood at 12.86 percent compared to 10.18 percent in June 2019.

He noted that construction works involving tunnels and viaducts along the 223km Dungun-Mentakab stretch (also known as Section B) was progressing according to plan.

“Site clearing and earthworks are actively taking place on multiple sites along Section B where there are no alignment changes to our Railway Scheme following the resumption of the improved ECRL project in April 2019,” he added.

The ECRL, scheduled for completion by December 2026, would have 640km rail network linking Kota Bharu to Port Klang.

The RM44 billion rail project is expected to cut travel time between Kota Bharu and Putrajaya in just four hours.

- Bernama

 


Please join the Malaysiakini WhatsApp Channel to get the latest news and views that matter.

ADS